The momentum on S549 slowed down a fair bit during 2017 as other priorities took hold.
The fitting of the firebox clothing continues, this time inside the cab.
 |
The new upper backhead sheet is trial fitted - January 2017 |
 |
Slow progress - upper & lower sheets trial fitted - July 2017 |
The barrel sheets are progressively fitted
 |
July 2017 |
 |
August 2017 |
 |
December 2017 |
Work inside the firebox
 |
The brick arch is placed back into position - October 2017 |
 |
The refitting of the fire grate is commenced - November 2017 |
Tender Clean Out
 |
Drums of ash & waste removed from the coal space |
 |