Sunday, December 6, 2015

5 December 2015 - Project Update



On Saturday the 5th of December we played around with the training module once again, the plan was to try out the pneumatic tooling, the tube set-up and expanding/beading techniques.

But firstly, following the initial trial on the training module, a number of items were identified to be obtained prior to giving the real test case a go; no use going full steam ahead if we are stuffing around with 1/2 of the required equipment. The list went like this;
  • 3/4 drive to Morse adaptor insert; the new tube rolling equipment mandrels are 3/4 drive and you guessed it, we had every size but..! That's where we get local industry involved and have components manufactured to our specifications. Pressform Engineering manufactured two new adaptors and they work a treat.
  • Corking gun - Loaned from a former WAGR boilermaker that happened to still have one in his cupboard, its not what you know but who you know.
  • Compressor - When we did the first trial, the volume of air that was available from the small compressor was good but for about 30 seconds, to install the tubes on the S would have taken more time than what's available in our lifetime anyway...! The word went out and Boulder Loopline came to the rescue with their compressor, thankyou.
One of the tasks we wanted to confirm today was the amount of tube projection from the firebox tube plate. I was always told that it should be between 3/16 and 1/4 of an inch but I wanted to confirm a length prior to installing all the tubes into the boiler. This is very important because too little projection runs the risk of damage to the tube plate when beading the tube, too much and there is the risk of poor beading due to excess material.
Drawing showing tube projection and flaring
So we set three tubes up, the first at 4.7625mm (3/16"), the next at 5.5mm and the last at 6.35mm (1/4") and with the use of the pneumatic motor and expanders we expanded and flared all three.We expanded and flared the three tubes at the firebox end first ensuring the projection was what we wanted, we then moved to the smoke box end and expanded the tubes at this end also.


Now for the beading. We purchased several beading tools when we ordered the expanders, we however found that they required a fair bit of shaping as initially they wanted to dig into the tube and cause damage, this took several goes to get right.
Typical beading tool
The Three Amigo's, following beading of the ends.
Note: damage to tube plate on the left and centre tubes due to insufficient
tube projection (4.76 and 5.5mm respectively).
The tube on the right was set at 6.35mm stick-out and beaded nicely.
Close up of the right (good) tube.
Drawing of expanded and beaded tube
We persevered with the small compressor for these three tube which added to the difficulty but never the less we achieved a fair bit today.

The plan for next week is to finalise our techniques and to train (give a go) the members of the team so we all know what is expected on the boiler.


Tuesday, October 27, 2015

24 October 2015 - Project Update

Firstly, apologies for the lack of updates but hopefully from this point forward we can fix that.
So what's been happening on 549..?
Well its been a slow six months in regards to progress on S549, a few things have however been going on both on and off the locomotive, so let me update you of what these are.

Electrical System Upgrade - A fair bit of work has been carried out on improvements to the electrical system by Alex and John. The aim is to modernise the lighting to LED lights with the exception of the headlights which will be Halogen Lights. To give justice to what work has gone into this so far, I will ask Alex to provide a report of which can be printed in a later update. We look forward to Alex returning to the project once his work commitments ease up.

Tube Installation - All the small tubes are now in the boiler.....yes, but they are not fitted, they still require expanding, beading and welding. Placing the tubes in the boiler was the easier of the tasks.
The new tubes waiting for collection, one by one.
The Tube Installer....
Aligning the tubes into the firebox tube plate
All fitted - Smokebox End
All Fitted - Firebox End
Alex - The Troglobite
Tube Expanding Equipment  -  The S class has 2-1/4 inch outside diameter tubes which is unique to all other WAGR boilers, the common size is 1-3/4 inch outside diameter tubes with the exception of the P, U, W and V classes of which were fitted with 2 inch outside diameter tubes. All the old WAGR expanding equipment for the S class was disposed of shortly after steam finished although the 1-3/4 and 2 inch was retained.

So we needed to purchase new tooling to expand and bead the tubes, but where do you obtain such equipment..? As the need for boilers did not die at the time of steam locomotives as they are still required in other industries, this equipment is available from several manufacturers but not the same type as the WAGR had commonly used.

Back in the WAGR days, they used a tapered roller type expander but these are now as rare as hens teeth as newer more efficient types have made them redundant.
There is nothing wrong with this type of expander as they have been used on Hotham Valleys W classes and on the Rail Heritage's G class re-tubing projects since the end of steam with excellent results. However they expand the tube greater on the outside edge of the tube plate than the inner edge giving a lesser of a seal on the inner edge.

So once advised that we could not obtain the original taper type expanders, we were required to research other styles that would do the job, this was carried out with correspondence to the manufacturers of the expanders providing them with the new tube dimensions, the dimensions of both tube plates and the finished  required dimensions noting overhang at both the firebox and smokebox ends.

As the boilermaker had only used the WAGR style in the past, it was decided that two sets would be obtained, 1 set each from two well known suppliers, this would ensure that in the case that there were any breakages, problems with there performance or other, we would have a contingency plan. These were ordered in July and arrived in August.

Of the expanders we ordered, there were two different types; the smokebox expander was required to take into account the 3/4 of an inch protrusion of the tube from the tube plate and the fire box expander also flared the ends for preperation of the beading. We also ordered beading tools to bead the ends on the firebox end.

It was also decided to set up a 1:1 scale training module of a section of the boiler with the length of the tubes reduced to 500mm long. The tubeplate sections were drawn in CAD with the same hole dimensions and pitch between hole centers as per the original S class WAGR drawings, these were then supplied to a local machine shop for manufacture.


The module will assist with the following;
  • Training - As the boilermaker has the only experience in the installation of tubes into steam locomotive boilers amongst the S549 team, it gives the opportunity for the other members of the team to have a go as there is zero risk in mucking them up, just knock them out and have another go. Lets face it, none of us are getting any younger and if the skills can be passed onto others especially the younger members then that's a good thing. The younger members of Bennett Brook Railway have also shown interest in observing the procedure once we have it all set-up.
  • The expanded interference or fit-up of the tube to the tubeplate can be checked to ensure a sure seal is obtained. This is done by calculating the tube wall reduction and we would rather test it on the module than on the locomotive. I'll go into the wall reduction at a later time.
  • As mentioned before, the expanders are a different type to that previously used on small tubes, so we can get to know them and choose which model/make perform the best to give us the wanted outcome.
  • Gives the opportunity for the boiler inspector to review the processes and the fit-up of the tube to the tubeplate in what would normally be the water space which can be difficult to do on the locomotive boiler.
Saturdays objective was to set the module up ready for trialing tube installation at a later date, this was done in the morning with the assistance from John Cole. We had no intention of going any further than this as we are planning to use a drive motor with a torque setting to fit the tubes and we had not yet organised this. We then inserted a few pre-prepared tubes and decided, what the heck, lets manually expand one of them as per what was done many years ago in the running sheds because we can't stuff them up.
The Test Module
So we set the fire box end at 3/16 of an inch protruding, wedged the smokebox end to stop the tube from trying to rotate and with the use of an old WAGR tube expanding ratchet we started to rotate the mandrel and expand the tube. This was tricky as the expander wanted to flare the end prior to fully expanding the tube, we will need to practice a bit to get it just right but that proves the advantage of the training module.
Tube Prior to Expansion - (Firebox End on Module)
Tube Post Expansion & Flaring- (Firebox End on Module)
Tube Expander - (Firebox End on Module)

We then expanded the smokebox end and had no real issues other than it taking longer to expand the tube at this end for some reason...
Tube Prior to Expansion - (Smokebox End on Module)
Tube Post Expansion - (Smokebox End on Module)
Tube Expander & Ratchet - (Smokebox End on Module)
Tube Expander & Ratchet - (Smokebox End on Module)
We only expanded one tube to get a feel of how things will go but next weekend we will do several more.

Well that's it for now, hopefully from this point forward work on her will increase rapidly.

Sunday, May 17, 2015

That Was Then - S549 - 1940's to 1971

Read about S549's time with the WAGR, she had a quite uneventful life but an interesting one all the same.

Click on the That Was Then - S549 - 1940's to 1971 page on the right or the link below, sit back and enjoy.

http://s549.blogspot.com.au/p/that-was-then.html

S class 549 Greenmount passing through Pinjarra,
Photo J. Joyce - Rail Heritage WA P06691